DGT Equipment Plan 2026: SA Port Adds 70 Machines

Straddle carrier moving a container at a Durban terminal as the DGT equipment plan 2026 adds 70 machines.

Durban, 25 November 2026 — The DGT equipment plan 2026 sets out how the Durban Gateway Terminal intends to clear its backlog. First, the terminal says 16 new reach stackers and empty-container handlers will arrive by the end of November. Then 26 second-hand straddle carriers follow in two batches by the end of March 2027. After that, 12 new straddle carriers arrive by the third quarter of 2027. Finally, 16 new rubber-tyred gantry cranes arrive in two batches, in December 2027 and March 2028.

Together, that is 70 machines over about 16 months. In the meantime, original equipment manufacturers are on site to repair the terminal’s existing ship-to-shore cranes and straddle carriers. DGT is also adding generators and backup power. In addition, it says its Navis N4 terminal operating system is now running smoothly.

Transnet’s Urgent Measures

Transnet announced a separate set of measures on 18 November. Specifically, the Transnet National Ports Authority has dedicated Maydon Wharf Berth 102 to geared vessels, which carry their own cranes. Some vessels are also being diverted to the Ngqura Container Terminal near Gqeberha. Meanwhile, all six ship-to-shore cranes at Pier 1 are back in operation, after the last one was commissioned on 20 November. Transnet Freight Rail has also made trains available to move import containers to Gauteng. However, Transnet Port Terminals cannot lend equipment from its Cape Town terminals for now, because of the peak deciduous-fruit export season.

Medicines And Essential Cargo First

Transnet is also prioritising essential cargo, such as pharmaceuticals and auto parts. Of 16 vessels on a Department of Health list, six had been completed by 20 November. Their containers had already left the port. At that point, three more were due to berth, one at Pier 1 and two at DGT. The remaining seven were still approaching, without a berth nominated.

Analysis

What The DGT Equipment Plan 2026 Means For Fleets

For hauliers, the plan works at two speeds. The reach stackers and second-hand straddle carriers should help within months. However, the rubber-tyred gantry cranes, which add yard capacity, only arrive from December 2027. Meanwhile, the South African Association of Freight Forwarders (SAAFF) puts DGT at about 3,300 moves a day. The target is 4,000 to 4,200. SAAFF’s Dr Jacob van Rensburg told The National that “it does not remove the need for DGT to build the productive capacity”.

On the landside, DGT says full import containers now take about three days from discharge to release. It is also rolling out a new truck appointment system, although the reports gave no details. In addition, KwaZulu-Natal Transport MEC Siboniso Duma has promised more traffic inspectors and Operation Shanela teams. He linked the congestion to truck accidents.

The Desk Calculation: The Moves Gap

Here are the sums, with the assumptions shown. The gap between about 3,300 moves a day and the 4,000 to 4,200 target is 700 to 900 moves a day. Assume each move is one container and that most containers arrive or leave by road. Then the shortfall equals up to 700 to 900 truck loads a day. That excludes boxes that go by rail or travel two to a truck. Over a 30-day month, that is up to about 21,000 to 27,000 loads.

Boxes diverted to Ngqura, by contrast, still move, but further. As the Durban port delays 2026 report showed, the trip from Gqeberha to Johannesburg adds about 480 km. On that report’s assumptions, the detour costs about R12,700 to R14,700 per load before tolls. Rail, therefore, is the cheaper route for any import box that can use it.

DGT Equipment Plan 2026: What Arrives When

EquipmentNumberTiming
Reach stackers and empty-container handlers (new)16By the end of November 2026
Straddle carriers (second-hand)26Two batches, by the end of March 2027
Straddle carriers (new)12By the third quarter of 2027
Rubber-tyred gantry cranes (new)16Two batches, December 2027 and March 2028
Total70November 2026 to March 2028

The Numbers Behind The DGT Equipment Plan 2026

70Machines in the plan, from November 2026 to March 2028
3,300Moves a day at DGT, while the target is 4,000 to 4,200
6Pier 1 ship-to-shore cranes back in operation

Fleet Impact

How Hauliers Can Work With The Plan

First, use the alternatives where they fit. Some import boxes can now move by rail to Gauteng, while others will land at Ngqura. Second, prepare for the new DGT truck appointment system, which follows the earlier DGT truck booking system changes. Vehicle tracking for fleet management records arrival and departure times at each gate. So hauliers can match trucks to slots and prove waiting time. In addition, Digit D-Fuel logs the litres burned in queues and on detours. As a result, each detour and each hour in a queue carries a fuel figure.

  • First, track appointment slots. A new DGT truck appointment system is being rolled out.
  • Second, consider rail. Transnet Freight Rail has trains available for import containers to Gauteng.
  • Third, price Ngqura loads. A box landed there instead of Durban adds about 480 km to the trip inland.
  • Finally, plan for 2028. The DGT equipment plan 2026 is only complete when the last gantry cranes arrive in March 2028.

Fleet Technology

Fleet Technology For A Terminal Rebuild

New equipment takes months to arrive. A haulier’s own waiting-time data, by contrast, is available now. DigitFMS tracking timestamps every arrival at the gate and every departure. Meanwhile, Digit D-Fuel measures the diesel burned while a truck waits. Therefore, a haulier can show how each change at the terminal affects its own turnaround. Tracking is also offered by Cartrack, Netstar, Tracker, Ctrack and MiX by Powerfleet. Installation and support are close at hand, with more than 100 DigitFMS branches in the network.

Key Numbers: DGT Equipment Plan 2026 At A Glance

Key Numbers · DGT Equipment Plan 2026

Equipment: 16 reach stackers and empty-container handlers (end November 2026); 26 second-hand straddle carriers (end March 2027)

Later: 12 new straddle carriers (third quarter 2027); 16 rubber-tyred gantry cranes (December 2027 and March 2028)

Transnet measures (18 November): Berth 102 for geared vessels, diversions to Ngqura, all six Pier 1 cranes operating, rail to Gauteng

Medicines: 16 vessels on the Department of Health list, so 6 completed, 3 due to berth and 7 approaching (20 November)

Productivity: about 3,300 moves a day, while the target is 4,000 to 4,200 (SAAFF)

Dwell: about three days from discharge to release for full import containers (DGT)

Desk calculation: 700 to 900 moves a day short ≈ up to 21,000 to 27,000 truck loads a month

Source: Transnet; DGT via The National and Sunday World; SAnews; SAAFF via The National.

Questions Answered

Frequently Asked Questions: DGT Equipment Plan 2026

What Is In The DGT Equipment Plan 2026?

The plan adds 70 machines: 16 reach stackers and empty-container handlers, 38 straddle carriers and 16 rubber-tyred gantry cranes. They arrive between November 2026 and March 2028.

When Will The New Gantry Cranes Arrive At DGT?

The 16 rubber-tyred gantry cranes arrive in two batches, in December 2027 and March 2028. Before that, manufacturers are repairing the existing cranes.

What Has Transnet Done To Reduce The Backlog?

Transnet dedicated Berth 102 to geared vessels and is diverting some ships to Ngqura. It also brought all six Pier 1 ship-to-shore cranes back into service and offered trains to Gauteng.

Are Medicines Being Prioritised At Durban Port?

Yes. Of 16 vessels on a Department of Health list, six were completed by 20 November. Meanwhile, three were due to berth and seven were still approaching.

Is DGT Changing How Trucks Book?

Yes. DGT says a new truck appointment system is being rolled out. However, the reports on the plan did not give its details.

How Fast Is DGT Working Now?

SAAFF puts DGT at about 3,300 moves a day, against a target of 4,000 to 4,200. Meanwhile, DGT says full import containers take about three days from discharge to release.

Facts checked 23 November 2026. Source: Transnet media statement, The National (21 November), The National (20 November), Sunday World and SAnews. Related: the DGT Navigate system and the TNPA separation.